What do these money figures mean?
Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

These are Norwich’s finances. County finances are separate. See County projects located here.

Filters1 active
Reset
reported current budget; amendments identified in rowscapital

Capital financial summary through August 31: amendments and carryforwards

Published interim capital schedule including prior-year projects, debt payments and grant credits interim capital reporting basis · 2026 · CAD · source accounting amounts; HST basis not specified on summary

Original approvedNot established
Revised authorization$7,801,523
Reported actual$2,820,764.49Through 2026-08-31
Published forecastNot established

Does the breakdown add up?

Source total $7,801,523Covered on the stated basis $7,801,523Reconciled difference $0

Current-budget leaf rows, not the original new-project allocation schedule. Actual leaf sum checked separately. Do not describe the difference from original $4,806,500 as a same-scope overrun.

Definitions, changes & interpretation
  • Mall Road reports 50% Norfolk in label but the reported actual is $1,422,313.53 versus a $714,000 2025 budget. Partner recovery and comparable net scope must be reconciled before calling it a Township overrun.
Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

What is the total made of?

Filters1 active
Clear row filters

62 matching accounts. Parent totals include the indented accounts. — means no published amount.

Reported actuals by service

Norwich · 2026 · interim capital reporting basis · Actual through 2026-08-31

  1. Mall Road (082/083/084) 50% Norfolk - 2025 Budget$1,422,313.53
  2. Pumper 7101 Replacement - Replaces 2000 GMC$755,160.35
  3. Fire Fighting Equipment - Per asset replacement program$129,174.30
  4. Diesel Exhaust Capture - Station 1, 2 and 4$97,847.43
  5. Debenture Payments - Norwich Community Ctr 2006-2026$71,672.64
  6. Provincial Grant - For diesel exhaust project-$69,418.58
  7. Works Pick-up Replacement - 2018 Silverado 1500$61,973.85
  8. HVAC Replacement - Station 2$38,865.10
  9. Debenture Payments - New Operations Centre$35,641.28
  10. NCC - Interior Paint - Arena area$34,452.86
  11. Hanmer Line Bridge No. 20 - Structural repair$31,569
  12. Firehouse Grant — struts purchase-$29,768.72
CAD · Largest 12 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below.
Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Capital financial summary through August 31: amendments and carryforwards · 2026 · interim capital reporting basis · CAD
Service / facility / accountRevised budgetActualEvidence
Furniture - Misc. furniture / filing cabinetsGeneral Government$5,000$3,816Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Computer Replacement Program - Per Township's replacement sch.General Government$7,500$7,088.86Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Administration Office Chairs - Excl. boardroom and Council cham.General Government$12,700$13,628.21Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Staff Workstations - For central work areaGeneral Government$22,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Council Chamber Desks - Budget Ammendment CAO 2026-06General Government$9,750$9,921.60Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Ceiling Light Replacement - Pendant lightsGeneral Government$6,500$7,275.84Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Otterville Park - 2025 Budget AmendmentGeneral Government$50,000$13,873.87Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Fire Fighting Equipment - Per asset replacement programProtective Services$130,000$129,174.30Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Computer Replacement Program - Per Township's replacement sch.Protective Services$4,700$3,966.76Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Communications System - sharedProtective Services$2,100$2,111.52Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Pumper 7101 Replacement - Replaces 2000 GMCProtective Services$755,000$755,160.35Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

HVAC Replacement - Station 2Protective Services$40,000$38,865.10Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Diesel Exhaust Capture - Station 1, 2 and 4Protective Services$100,000$97,847.43Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Provincial Grant - For diesel exhaust projectProtective Services$0-$69,418.58Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Building Department - Tablets (2025 Budget)Protective Services$2,400$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Debenture Payments - Station 2 2009-2028Protective Services$39,722$20,056.56Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Debenture Payments - Tanker Truck 2010-2029Protective Services$11,690$5,894.59Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Debenture Payments - Station 3 2019-2038Protective Services$42,241$21,185.74Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Debenture Payments - Aerial Fire Apparatus 2021-2040Protective Services$58,332$29,286.49Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Brock Street W Norwich (201A) [FD] - Cons. Area to Stover St. NTransportation Services$1,620,000$14,711.83Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Smiths Lane (274) [FD] - McNab to HWY 59Transportation Services$110,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Church Street (252/123) [FD] - North St. W to Pick Line (2025 Bud)Transportation Services$56,300$9,374.64Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Mall Road (082/083/084) 50% Norfolk - 2025 BudgetTransportation Services$714,000$1,422,313.53Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Guiderail Program - Middletown LineTransportation Services$100,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Cracksealing Program - Preventative maintenanceTransportation Services$50,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Substation Road (027) Grvl Conv. - Per OP 2026-12 (Budget Ammend.)Transportation Services$1,026,100$3,451.08Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Beaconsfield Rd. (033A) Grvl Conv. - Per OP 2026-12 (Budget Ammend.)Transportation Services$771,000$3,373.96Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Vandecar Line Bridge No. 6 - To Close the Bridge (2025 Budget)Transportation Services$250,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Hanmer Line Bridge No. 20 - Structural repairTransportation Services$55,000$31,569Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Maple Dell Road Bridge No. 24 - Replace failed joint sealsTransportation Services$35,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Evergreen Street Culvert No. 7 - Engineering for 2027 replacementTransportation Services$87,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Assorted Culverts less than 3m - ReplaceTransportation Services$35,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Zenda Line Box Culvert (SWOX 50%) - Replace (2025 Budget)Transportation Services$35,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Middletown Line Lot - *2024 Project* - Base and FenceTransportation Services$20,000$4,031.73Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Sidewalks Replacement - Misc locations based on inspectonsTransportation Services$20,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Sidewalk Urbanization Project - Burgessville (County)Transportation Services$120,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Streetlight Urbanization Project - Burgessville (County)Transportation Services$60,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Works Pick-up Replacement - 2018 Silverado 1500Transportation Services$65,000$61,973.85Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Works S/A Dump 57 Replacement - 2012 InternationalTransportation Services$400,000$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

Burgessville Works Yard - Residential Units (Report FS 2022- 03Transportation Services$0$0Through 2026-08-31
Details & source

Interim reported budget includes prior-year carryforwards/amendments where labelled. Published dash means zero. Grant credits and debt service are included in this source schedule.

Source location: p.1

Open the source record
  1. FS 2026-15 — Capital financial summary pages 1–2

    Township of Norwich · Published 2026-09-22 · Event/reporting date 2026-09-22 · 2026 through August 31

    report presented for information · Primary record verified · Interim amounts, not final-year outcomes.

From an allocation to a result

Norwich · Parks, recreation & culture

Otterville pool replacement: preliminary design and grant application

A grant application and up-to-$60,000 preliminary consulting authority have been approved. Full pool construction is not funded by this authorization.

Norwich

Preliminary consulting authorized; construction and grant award not established
Original budget
$60,000
Next target
No next date listed
Latest update
2026-09-08 · Otterville pool: grant application and preliminary design

Norwich · Roads & bridges

Beaconsfield and Substation road conversion package

Two gravel-road conversions share reconstruction and surface-treatment awards. The Township also plans an 800-metre full-load asphalt section of Substation Road, with the additional full-load cost to be paid by the neighbouring property owner under a future agreement.

Norwich

Two contracts awarded; asphalt agreement and final funding unresolved in reviewed record
Original budget
$1,797,160
Named suppliers
South Brant Excavating Inc.; Walker Construction Limited
Next target
No next date listed
Latest update
2026-08-31 · Spending reported through this date

Norwich · Roads & bridges

Brock Street West reconstruction

Council awarded Brock Street reconstruction to Navacon. The May cost forecast for Norwich’s share was $1.885 million against a $1.620 million original budget.

Norwich

Spending reported · completion unconfirmed
Revised budget
$1,620,000
Named supplier
Navacon Construction Inc.
Next target
No next date listed
Latest update
2026-08-31 · Financial reporting cutoff

Norwich · Other projects

Council Chamber Desks - Budget Ammendment CAO 2026-06

Council Chamber Desks - Budget Ammendment CAO 2026-06

Norwich

Spending reported · completion unconfirmed
Revised budget
$9,750
Next target
No next date listed
Latest update
2026-08-31 · Financial reporting cutoff

Norwich · Fire & public safety

Diesel Exhaust Capture - Station 1, 2 and 4

Diesel Exhaust Capture - Station 1, 2 and 4

Norwich

Spending reported · completion unconfirmed
Revised budget
$100,000
Next target
No next date listed
Latest update
2026-08-31 · Financial reporting cutoff

Norwich · Parks, recreation & culture

NCC - Interior Paint - Arena area

NCC - Interior Paint - Arena area

Norwich

Spending reported · completion unconfirmed
Revised budget
$120,000
Next target
No next date listed
Latest update
2026-08-31 · Financial reporting cutoff