Otterville pool replacement

Money & projects Explore sections
Norwich Township project

At a glance

Original project title

Otterville pool replacement: preliminary design and grant application

Location
Norwich
Responsible authority
Norwich Township
Current stage
Grant/design motion lost in adopted minutes; whole project separateAs of 2026-10-13
Historical September 8 consulting ceiling
$60,000
Next target
No next date listed

October 13 adopted minutes record reconsideration of the September 8 motion, defeat of the grant application and preliminary-design authority of up to $60,000, and receipt of CAO2026-29 for information. This does not establish cancellation of the whole pool-replacement project. The October 13 minutes were adopted November 3 under resolution 2. Adoption confirms the written record; it does not add a construction, payment or completion decision.

October 13 adopted minutes record reconsideration of the September 8 motion, defeat of the grant application and preliminary-design authority of up to $60,000, and receipt of CAO2026-29 for information. This does not establish cancellation of the whole pool-replacement project.

Who approves and delivers this project?

Approves funding

Township Council

Approves reserve draw and scope.

Execution

Chief Administrative Officer

Staff implementation depends on current Council authority. Adopted October 13 minutes record defeat of the September grant/design motion.

Money

Project money

Budget and forecast

Historical September 8 consulting ceiling
$60,000

Latest spending total not published here.

CAD · as stated in authorization · Historical September 8 consulting ceiling; that grant/design motion was defeated in the adopted October 13 record. No current construction budget is established.

Historical funding authority

$60,000Historical listed funding

  1. Otterville Pool ReserveHistorical September 8 reserve ceiling; the grant/design motion was later defeated. Not money spent.
    $60,000100% of listed total
Listed funding adds to the original budget amount. Historical funding is retained for context; see the current decision and funding qualifications. CAD.

Timeline

  1. caption indicated outcome

    Grant/design motion lost on reconsideration — captions

    Historical October 29-30 review: October 13 meeting captions record reconsideration and defeat of the September 8 grant/design motion, including its up-to-$60,000 consulting authorization. CAO 2026-29 was then received for information. Written October 13 minutes and independent audio verification were not available in this audit; this is not evidence that the entire pool-replacement project was cancelled.

  2. review

    Pool design-and-grant motion was defeated; whole project not cancelled

    Historical October 29-30 review: Draft minutes record defeat of the proposed recreation-grant application and single-source preliminary pool design allocation of up to $60,000. Council then received the report for information. Draft pending November 3 adoption. Does not establish cancellation of the whole pool project; no individual recorded vote count stated.

  3. decision

    Grant/design motion lost; report received

    October 13 adopted minutes record reconsideration of the September 8 motion, defeat of the grant application and preliminary-design authority of up to $60,000, and receipt of CAO2026-29 for information. This does not establish cancellation of the whole pool-replacement project.

  4. record adoption

    October 13 minutes adopted

    The October 13 minutes were adopted November 3 under resolution 2. Adoption confirms the written record; it does not add a construction, payment or completion decision.

Contracts

Contract award not confirmed.

Decisions

2026-09-08 · Resolution23

Otterville pool: grant application and preliminary design

Carried

$60,000 · Historical September 8 maximum consulting authority; the grant/design motion was defeated on October 13. This is not a current allocation or actual spending.

Consequence: The September 8 carried decision remains historical. October 13 adopted minutes record reconsideration of the September 8 motion, defeat of the grant application and preliminary-design authority of up to $60,000, and receipt of CAO2026-29 for information. This does not establish cancellation of the whole pool-replacement project.

2026-10-13 · CAO 2026-29

Pool grant/design motion defeated in adopted minutes

Reconsideration carried; grant/design motion lost; report received

Consequence: October 13 adopted minutes record reconsideration of the September 8 motion, defeat of the grant application and preliminary-design authority of up to $60,000, and receipt of CAO2026-29 for information. This does not establish cancellation of the whole pool-replacement project.

Outcomes

No construction approval, grant award or completed replacement established.

Questions

  • What do the adopted October 13 minutes and subsequent directions establish about current grant/design authority?
  • What remains proposed for pool services, capital costs and ongoing operations?

Related issues

What is the current authority and next decision for Otterville Pool?
Scope & interpretation notes
  • The $60,000 ceiling remains historical and is not a current annual allocation or amount spent. No construction approval, grant award or final project cancellation is inferred. The October 13 minutes were adopted November 3 under resolution 2. Adoption confirms the written record; it does not add a construction, payment or completion decision.

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. CAO 2026-29 — Otterville pool grant application

    Source ID: norwich-pool-grant-report

    Publisher
    Township of Norwich
    Published
    2026-09-08
    Event / reporting date
    2026-09-08
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    published staff report
    Passage / page
    full report
    Evidence notes
    Downloaded and extracted underlying primary PDF.

    Open in source library

  2. Council minutes 09/08

    Source ID: norwich-minutes-09-08

    Publisher
    Township of Norwich
    Published
    2026-09-08
    Event / reporting date
    2026-09-08
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    adopted minutes
    Passage / page
    relevant resolution noted in connected record

    Open in source library

  3. October 13 Council recording — full available captions reviewed

    Source ID: norwich-oct13-captions-2026

    Publisher
    Township of Norwich
    Source date
    2026-10-13
    Published
    2026-10-13
    Event / reporting date
    2026-10-13
    Reviewed
    2026-10-29
    Retrieved
    2026-10-29
    Verified
    2026-10-29
    Evidence status
    caption_reviewed
    Decision / approval status
    Caption-indicated; written minutes pending
    Evidence type
    automatic_captions
    Evidence qualification
    moderate
    Passage / page
    1,356 displayed cues, 13:03–3:12:57; runtime 3:13:21
    Evidence note
    Full available October 13 captions reviewed October 29; audio and visual voting were not independently verified. Written October 13 minutes were not available in this audit.
    Evidence notes
    Full available October 13 captions reviewed October 29; audio and visual voting were not independently verified. Written October 13 minutes were not available in this audit.
    Caption passages
    1356
    Audio independently verified
    false
    Visual vote verified
    false

    Open in source library

  4. Pool design-and-grant motion was defeated; whole project not cancelled

    Source ID: oct30-nor-pool-design-motion

    Source date
    2026-10-13
    Event / reporting date
    2026-10-13
    Reviewed
    2026-10-30
    Retrieved
    2026-10-30
    Evidence status
    verified_primary
    Decision / approval status
    motion lost; report received for information
    Passage / page
    Resolutions 23–25; resolution 24 lost, resolution 25 carried
    Evidence note
    Primary-source body reviewed in the October 30 audit Draft pending November 3 adoption. Does not establish cancellation of the whole pool project; no individual recorded vote count stated.

    Open in source library

  5. Adopted October 13 minutes: pool grant and design motion

    Source ID: nov7-norwich-pool-adopted-minutes

    Source date
    2026-10-13
    Event / reporting date
    2026-10-13
    Reviewed
    2026-11-07
    Evidence status
    verified_primary
    Passage / page
    Pages 13-14, resolutions 23-25; page 15 adoption certification
    Evidence note
    Resolution 23 carried reconsideration, resolution 24 lost the grant/preliminary-design motion and resolution 25 received CAO2026-29 for information. This is not cancellation of the whole pool project. No individual voting positions or vote count are recorded.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

Open the full money explanation