Council awarded Brock Street reconstruction to Navacon. The May cost forecast for Norwich’s share was $1.885 million against a $1.620 million original budget.
Brock Street W Norwich (201A) [FD] - Cons. Area to Stover St. N
Who approves and delivers this project?
Budget approval
Township of Norwich Council
Township authority; departmental delivery subject to report-specific approvals.
Road Construction ReserveMay 26 forecast; $24,401.30 above the original $758,058 reserve contribution.
$782,459.3041.5% of listed total
Development chargesMay 26 forecast; Council authorized use for Brock Street. Allocation shown in report: $219,567 residential and $20,732 non-residential.
$240,29912.7% of listed total
Listed funding adds to the forecast amount. CAD.
Timeline
award
Tender awarded; financing change authorized
Navacon awarded PW-2026-02. Township-share forecast includes additional hydro and inspection estimates.
The published bid does not establish the final executed contract value. Full tender bid before tax; Township construction share in report is net of HST rebate.
Council awarded tenderPW-2026-02 to the report’s lowest compliant bidder. Published full bid includes Norwich, Oxford County and private-development portions. Minutes do not restate dollar value; signed agreement not obtained. Retain bid field as bid instead of implying a reconciled final contract value.
Consequence: May 26 Resolution 9 awarded PW-2026-02 Brock Street reconstruction to Navacon and allowed use of development-charge funds. The supplied minutes extract does not establish an award amount or completion.
One shared project record; financial schedule also displays this line. Do not count both as separate expenditure. Original allocation paired to exact department/facility/asset row in adopted capital schedule.
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
pp.2–4; bid table p2 and Township costs/funding table p3
Evidence notes
Full primary PDF downloaded and text extracted. Financial table p3 visually checked. Whole tender includes Township, County and private-development shares; Township-share estimates are net of HST rebate. Report contains Navicon spelling in prose; recommendation, bid table and adopted minutes name Navacon.