Published interim financial report; not audited year-end resultsinterim actuals
Operating expenditure at September 30, 2026
Operating expenditure at September 30, 2026 Dated gross expenditure summary · 2026 · CAD · Not specified in inspected table
Original approved$12,438,600
Revised authorizationNot established
Reported actual$8,742,606Through 2026-09-30
Published forecastNot established
Does the breakdown add up?
Source total $12,438,600Covered on the stated basis Not establishedUnreconciled / unextracted remainder Not established
Only rows from this schedule are included. Parent totals and child detail must not be added together.
Definitions, changes & interpretation
The operating summary reports $8,742,606 spent against a $12,438,600 budget. The capital expense table reports $2,893,824.26 against $7,801,523. These are September 30 figures, not October 30 actuals or final savings. Capital includes carry-forwards, cost-sharing and grant offsets. Unspent balances are not surplus or completion; Mall Road gross spending is not a reconciled net overrun. Staff flag fuel spending above $220,000 versus $182,000 at the same time last year, vehicle maintenance $58,230 over budget following an $84,000 grader engine replacement, and grading materials approximately $60,000 over budget after freeze/thaw cycles. Partial-year comparison; staff also note seasonal timing and no significant regular-business concerns overall.
Operating expenditure at September 30, 2026 · 2026 · Dated gross expenditure summary · CAD
Service / facility / account
Evidence
No rows match. Clear the filters or choose another schedule.
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Primary-source body reviewed in the October 30 audit Capital includes carry-forwards, cost-sharing and grant offsets. Unspent balances are not surplus or completion; Mall Road gross spending is not a reconciled net overrun.
Primary-source body reviewed in the October 30 audit Capital includes carry-forwards, cost-sharing and grant offsets. Unspent balances are not surplus or completion; Mall Road gross spending is not a reconciled net overrun.
October 13 adopted minutes record reconsideration of the September 8 motion, defeat of the grant application and preliminary-design authority of up to $60,000, and receipt of CAO2026-29 for information. This does not establish cancellation of the whole pool-replacement project. The October 13 minutes were adopted November 3 under resolution 2. Adoption confirms the written record; it does not add a construction, payment or completion decision.
Norwich
Grant/design motion lost in adopted minutes; whole project separate
October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.
Norwich
Asphalt award in adopted minutes; execution and completion unverified
Original budget
$1,797,160
Named suppliers
South Brant Excavating Inc.; Walker Construction Limited; Permanent Paving Ltd.
Council awarded Brock Street reconstruction to Navacon. The May cost forecast for Norwich’s share was $1.885 million against a $1.620 million original budget.
Council approved the property proposal in principle on September 8, 2026 and requested a working group and a fully costed plan and design to return in Q1 2027 for a final decision. A final construction budget, completed property transaction or open new facility is not established by the cited records.