02Follow the moneyNorwich

Norwich Township · Money

Follow the money.

Open the allocation. Check the actuals. Follow the decision into delivery.

Money & projects Explore sections
What do these money figures mean?
Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

These are Norwich’s finances. County finances are separate. See County projects located here.

Filters1 active
Reset
adoptedcapital

2026 adopted capital project allocations and ten-year forecast

New adopted project allocations; separate from capital tax levy and interim carryforward schedule capital allocation · 2026 · CAD · as budgeted

Original approved$4,806,500
Revised authorizationNot established
Reported actualNot establishedNo reporting cutoff established
Published forecastNot established

Does the breakdown add up?

Source total $4,806,500Covered on the stated basis $4,806,500Reconciled difference $0

All 2026 leaf allocations reconcile exactly. Source future-year rows total $56,654,540 versus the printed $56,639,540 overall ten-year figure; do not present the unreconciled forecast total as verified.

Definitions, changes & interpretation
  • Capital levy $4,475,600 finances reserve contributions and tax-supported debt servicing; it is not the $4,806,500 project allocation total.

What is the total made of?

FiltersRefine results
Clear row filters

309 matching accounts. Parent totals include the indented accounts. — means no published amount.

Allocation by service

Norwich · 2026 · capital allocation · original

  1. Brock Street W Norwich (201A) [FD] — Cons. Area to Stover St. N$1,620,000
  2. Pumper 7101 — 2025 International$755,000
  3. To Be Determined (Working Group)$500,000
  4. Works S/A Dump 57 — 2012 Int'l$400,000
  5. Firefighting Equipment Program$130,000
  6. Urbanization Project (County) — Burgessville$120,000
  7. NCC - Interior Paint$120,000
  8. Smiths Lane (274) [FD] — McNab to HWY 59$110,000
  9. Diesel Exhaust Capture — Stations 1,2 and 4$100,000
  10. Guiderail Program$100,000
  11. NCC Boilers$100,000
  12. Tractor — 2014 Kubota$95,000
CAD · Largest 12 extracted rows by absolute magnitude on this basis. Signed inflows or recoveries retain their minus sign. The full accessible table and sources are below.
2026 adopted capital project allocations and ten-year forecast · 2026 · capital allocation · CAD
Service / facility / accountOriginal budgetEvidence
New Councillor TechnologyGeneral government$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

FurnitureGeneral government$5,000
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

Delivery record: Furniture - Misc. furniture / filing cabinets

Computer Replacement ProgramGeneral government$7,500
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

Delivery record: Computer Replacement Program - Per Township's replacement sch.

Administration Office ChairsGeneral government$12,700
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

Delivery record: Administration Office Chairs - Excl. boardroom and Council cham.

Staff WorkstationsGeneral government$22,000
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

Delivery record: Staff Workstations - For central work area

Records Management SystemGeneral government$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

Upgraded Financial SoftwareGeneral government$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

Administration Building - Capital RepairsGeneral government$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

Facility Assessment — All FacilitiesGeneral government$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

SidingGeneral government$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

Wireless RoutersGeneral government$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

Ceiling Light ReplacementGeneral government$6,500
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.15

Delivery record: Ceiling Light Replacement - Pendant lights

Firefighting Equipment ProgramProtective services$130,000
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Delivery record: Fire Fighting Equipment - Per asset replacement program

Computer EquipmentProtective services$4,700
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Delivery record: Computer Replacement Program - Per Township's replacement sch.

Communications System (shared)Protective services$2,100
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Delivery record: Communications System - shared

SCBA, Cylinders and RITProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Breathing Air CompressorProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Washing Station - Bunker GearProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Digital SignsProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Staff Truck — 2020 Chevrolet 1500Protective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Pumper 7101 — 2025 InternationalProtective services$755,000
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Delivery record: Pumper 7101 Replacement - Replaces 2000 GMC

Pumper 7201 (Aerial) — 2021 Rosenbauer CobraProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Pumper 7301 — 2007 FreightlinerProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Pumper 7401 — 2025 InternationalProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Tanker 7102 — 2016 InternationalProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Tanker 7202 — 2023 FreightlinerProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Tanker 7302 — 2000 GMC Top-KickProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Tanker 7402 — 2009 FreightlinerProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Rescue 3 — 2021 Frtlnr/RosenbauerProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Fire Halls - Capital Repairs — Station 1Protective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Fire Halls - Capital Repairs — Station 2Protective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Fire Halls - Capital Repairs — Station 3Protective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Fire Halls - Capital Repairs — Station 4Protective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Station 2 HVAC — Station 2Protective services$40,000
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Delivery record: HVAC Replacement - Station 2

Diesel Exhaust Capture — Stations 1,2 and 4Protective services$100,000
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Delivery record: Diesel Exhaust Capture - Station 1, 2 and 4

Building Vehicle — 2024 Chevrolet 1500Protective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Drains/Building Vehicle — 2019 Ford F150Protective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

TabletsProtective services$0
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.16

Brock Street W Norwich (201A) [FD] — Cons. Area to Stover St. NTransportation services$1,620,000
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.17

Delivery record: Brock Street W Norwich (201A) [FD] - Cons. Area to Stover St. N

Smiths Lane (274) [FD] — McNab to HWY 59Transportation services$110,000
Details & source

2026 adopted allocation. Future years are forecasts. Ten-year funding columns cover the entire 2026–2035 row, not only the 2026 allocation.

Source location: PDF p.17

Delivery record: Smiths Lane (274) [FD] - McNab to HWY 59

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. 2026 Ten Year Capital Budget and Forecast — Schedule A to By-law 02-2026

    Source ID: norwich-capital-2026

    Publisher
    Township of Norwich
    Published
    2026-01-13
    Event / reporting date
    2026-01-13
    Reporting period
    2026; forecast 2027–2035
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    adopted By-law 02-2026
    Passage / page
    PDF pages 2–26 (printed pages 1–25)
    Evidence notes
    Some internal headings say Proposed; adoption confirmed in January 13 minutes. 2027–2035 are forecasts, not current-year authorizations.

    Open in source library

From an allocation to a result

Norwich · Parks, recreation & culture

Otterville pool replacement

October 13 adopted minutes record reconsideration of the September 8 motion, defeat of the grant application and preliminary-design authority of up to $60,000, and receipt of CAO2026-29 for information. This does not establish cancellation of the whole pool-replacement project. The October 13 minutes were adopted November 3 under resolution 2. Adoption confirms the written record; it does not add a construction, payment or completion decision.

Norwich

Grant/design motion lost in adopted minutes; whole project separate
Historical September 8 consulting ceiling
$60,000
Next target
No next date listed
Latest update
2026-11-03 · October 13 minutes adopted

Norwich · Roads & bridges

Beaconsfield and Substation road conversion package

October 13 adopted minutes record a formal tender waiver and a $183,741 award to Permanent Paving Ltd., plus the Township’s non-refundable portion of HST, for a section of Substation Road asphalt. Council authorized the contractor agreement and an Oxford Cattle Company agreement covering the incremental asphalt cost above double surface treatment. Signed agreements, payments and completion are not established. The earlier report’s 2027 surface-treatment forecast remains a dated plan.

Norwich

Asphalt award in adopted minutes; execution and completion unverified
Original budget
$1,797,160
Named suppliers
South Brant Excavating Inc.; Walker Construction Limited; Permanent Paving Ltd.
Next target
No next date listed
Latest update
2026-11-03 · October 13 minutes adopted

Norwich · Roads & bridges

Brock Street West reconstruction

Council awarded Brock Street reconstruction to Navacon. The May cost forecast for Norwich’s share was $1.885 million against a $1.620 million original budget.

Norwich

Spending reported · completion unconfirmed
Revised budget
$1,620,000
Named supplier
Navacon Construction Inc.
Next target
No next date listed
Latest update
2026-08-31 · Financial reporting cutoff

Norwich · Buildings & facilities

Norwich Medical Centre proposal

Council approved the property proposal in principle on September 8, 2026 and requested a working group and a fully costed plan and design to return in Q1 2027 for a final decision. A final construction budget, completed property transaction or open new facility is not established by the cited records.

Norwich

Approved in principle; costed plan requested
2026 allocation
Not established
Next target
2027 · Q1 2027: costed plan and design requested
Latest update
2026-11-03 · October 13 minutes adopted

Norwich · Other projects

Council Chamber Desks - Budget Ammendment CAO 2026-06

Council Chamber Desks - Budget Ammendment CAO 2026-06

Norwich

Spending reported · completion unconfirmed
Revised budget
$9,750
Next target
No next date listed
Latest update
2026-08-31 · Financial reporting cutoff

Norwich · Fire & public safety

Diesel Exhaust Capture - Station 1, 2 and 4

Diesel Exhaust Capture - Station 1, 2 and 4

Norwich

Spending reported · completion unconfirmed
Revised budget
$100,000
Next target
No next date listed
Latest update
2026-08-31 · Financial reporting cutoff
Explore all projects