Award / contractAmount not publishedNavacon Construction Inc. · 2026-05-26
Recorded paymentsAmount not publishedNo payment amounts attached
Full tender bid before tax; Township construction share in report is net of HST rebate. · Bid, award and payment are separate measures. A bid is not the final executed contract value.
Council awarded tenderPW-2026-02 to the report’s lowest compliant bidder. Published full bid includes Norwich, Oxford County and private-development portions. Minutes do not restate dollar value; signed agreement not obtained. Retain bid field as bid instead of implying a reconciled final contract value.
Council awarded Brock Street reconstruction to Navacon. The May cost forecast for Norwich’s share was $1.885 million against a $1.620 million original budget.
Norwich
Spending reported · completion unconfirmed
Revised budget
$1,620,000
Named supplier
Navacon Construction Inc.
Next target
No next date listed
Latest update
2026-08-31 · Financial reporting cutoff
Open project →
What still needs an answer
What is the executed contract value and allocation between the three parties?
What is the current completion date and final Township share?
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
pp.2–4; bid table p2 and Township costs/funding table p3
Evidence notes
Full primary PDF downloaded and text extracted. Financial table p3 visually checked. Whole tender includes Township, County and private-development shares; Township-share estimates are net of HST rebate. Report contains Navicon spelling in prose; recommendation, bid table and adopted minutes name Navacon.