Norwich Township project
On this page Overview Money Timeline Contracts Decisions Outcomes Questions Evidence At a glance
Location Norwich
Responsible authority Norwich Township Current stage Tender procurement authorized; award not establishedAs of 2026-09-08 Stage and project evidence: [1] [2] [3] [4]
Revised budget $100,000
Next target No next date listed Replace deteriorating north-end arena heating with high-efficiency condensing water heaters. Equipment estimate $60,000 before HST excludes installation, piping, venting and electrical work.
NCC Boilers - Two boilers and tanks
Who approves and delivers this project? Budget approval
Township of Norwich Council Township authority; departmental delivery subject to report-specific approvals.
Sources for this record: [5]
Money Published budget unchanged: $100,000
Project money Annual allocation 2026 allocation $100,000 Current reported capital budget, including carryforward where labelled Recorded spending Expenditure through 2026-08-31 $0 CAD · source accounting basis; not specified on interim summary · Current reported capital budget, including carryforward where labelled Project money evidence: [1] [2] [3] [4]
Find this project in the budget Where the funding comes from $100,000 Listed funding total
$100,000100% of listed total Listed funding adds to the revised budget amount. CAD. Timeline 2026-03-10 decision Specialist assessment requested Council chose assessment before major capital investment.
Sources for this record: [3]
2026-08-31 report Financial reporting cutoff Reported spending does not establish physical completion.
Sources for this record: [1]
2026-09-08 procurement Tender procurement authorized 100,000 annual budget. Estimated equipment lead time four to five weeks after order, not a confirmed completion date.
Sources for this record: [3] [4]
Contracts Contract award not confirmed.
Decisions No separate decision record is linked. Approval details may appear in the timeline or source documents.
Outcomes Completion not confirmed.
Questions What is the awarded installed price and delivery date? Will the approximately $600 annual maintenance program be funded? Scope & interpretation notes One shared project record; financial schedule also displays this line. Do not count both as separate expenditure. Original allocation paired to exact department/facility/asset row in adopted capital schedule. Sources & evidence These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: norwich-fs2026-15-capital
Publisher Township of Norwich
Published 2026-09-22
Event / reporting date 2026-09-22
Reporting period 2026 through August 31
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status report presented for information
Passage / page pages 1–2
Evidence notes Interim amounts, not final-year outcomes. Open in source library
Source ID: norwich-capital-2026
Publisher Township of Norwich
Published 2026-01-13
Event / reporting date 2026-01-13
Reporting period 2026; forecast 2027–2035
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status adopted By-law 02-2026
Passage / page PDF pages 2–26 (printed pages 1–25)
Evidence notes Some internal headings say Proposed; adoption confirmed in January 13 minutes. 2027–2035 are forecasts, not current-year authorizations. Open in source library
Source ID: norwich-arena-boiler-update
Publisher Township of Norwich
Published 2026-09-08
Event / reporting date 2026-09-08
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status published staff report
Passage / page pp.1–3
Evidence notes Downloaded and extracted underlying primary PDF. Open in source library
Source ID: norwich-minutes-09-08
Publisher Township of Norwich
Published 2026-09-08
Event / reporting date 2026-09-08
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status adopted minutes
Passage / page relevant resolution noted in connected record Open in source library
Source ID: norwich-minutes-01-13
Publisher Township of Norwich
Published 2026-01-13
Event / reporting date 2026-01-13
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status adopted minutes
Passage / page relevant resolution noted in connected record Open in source library
Copy this view Print