Norwich Township project
On this page Overview Money Timeline Contracts Decisions Outcomes Questions Evidence At a glance
Location Norwich
Responsible authority Norwich Township Current stage Cost-sharing agreement authorized; completion not verifiedAs of 2026-08-11 Stage and project evidence: [1] [2]
Original budget $65,000
Next target No next date listed Township funds catchbasins and ditch/culvert removal serving existing properties while developer funds its subdivision pipe, outlet and oil-grit separator.
Who approves and delivers this project? Approves funding
Township Council Approves reserve draw and scope.
Sources for this record: [1] [2]
Execution
Chief Administrative Officer Executes authorized cost-sharing/consulting steps within Council authority.
Sources for this record: [1] [2]
Money Project money Annual allocation 2026 allocation $65,000 upset authorization; not complete project lifetime cost Latest spending total not published here.
CAD · as stated in authorization · upset authorization; not complete project lifetime cost Project money evidence: [1] [2]
Where the funding comes from $65,000 Listed funding total
$65,000100% of listed total Listed funding adds to the 2026 allocation amount. CAD. Timeline No dated delivery milestones are published in this record.
Contracts Contract award not confirmed.
Decisions 2026-08-11 · Resolution24
Carried
$65,000 · upset reserve transfer authorization
Consequence: Developer pays subdivision stormwater pipe, outlet and separator; Township pays additional catchbasins, ditch/culvert removal and contribution to engineering.
Sources for this record: [2] [1]
Outcomes Completion not confirmed.
Questions What final agreement and actual Township cost followed the $65,000 authorization? Scope & interpretation notes Do not count authorization as money spent. Sources & evidence These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: norwich-burgess-stormwater-report
Publisher Township of Norwich
Published 2026-08-11
Event / reporting date 2026-08-11
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status published staff report
Passage / page pp.1,3–4
Evidence notes Downloaded and extracted underlying primary PDF. Open in source library
Source ID: norwich-minutes-08-11
Publisher Township of Norwich
Published 2026-08-11
Event / reporting date 2026-08-11
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status adopted minutes
Passage / page pp.12–15 resolutions 18, 19, 24; p.17 by-laws
Evidence notes Downloaded and extracted underlying primary PDF. Open in source library
Copy this view Print