Current documented stage Construction
Timing May–October 2026, tentative
Responsible authority Oxford County
What’s proposed or underway? The published project limits extend from approximately 150 metres west of Deer Crescent to approximately 150 metres east of Smiths Lane.
Work is phased, with detours and local access arrangements described in County project notices.
This is a County project within Norwich Township. The County project page is the source for construction timing and traffic changes.
Community photograph; not an image of current construction. Photo credits Follow the public funding and delivery One County-led Church Street reconstruction with separately identified Norwich sidewalk and streetlight components. Do not merge authority or sum these into a new total.
County · Roads & bridges
Urbanize Oxford Road 59 across Burgessville with road, sidewalk and lighting upgrades.
Norwich
Current October 2026 target; completion not verified
2026 allocation $4,100,000
Named supplier GIP Paving Inc.
Next target 2026-10 · Published completion target
Latest update 2026-08-12 · OR59 Church Street urbanization Burgessville Open project → Norwich · Roads & bridges
Sidewalk Urbanization Project - Burgessville (County)
Norwich
Spending reported · completion unconfirmed
Revised budget $120,000
Next target No next date listed
Latest update 2026-08-31 · Financial reporting cutoff Open project → Norwich · Roads & bridges
Streetlight Urbanization Project - Burgessville (County)
Norwich
Spending reported · completion unconfirmed
Revised budget $60,000
Next target No next date listed
Latest update 2026-08-31 · Financial reporting cutoff Open project →